Microsoft Horizon data centers at Childress

Company: IREN - Project: Childress

Subject kind
facility capacity
Statement date
2026-08-13
Promised amount
200.0 MW
Current status
stated

The claim, verbatim

IREN is building four 50MW AI data center tranches totaling 200MW at its Childress, Texas campus for Microsoft

Source (primary)

IREN Microsoft AI deal clears first hurdle, shares jump 10% - ABC Money (-, news_article)
View cached copy (2026-08-31)Live source ↗

Quote: “Horizon 1 is the first of four planned 50MW tranches, together making up 200MW”

How we checked this

Checked on September 19, 2026. The cited source supports every part of this claim.

The document states Horizon 1 is the first of four 50MW tranches totaling 200MW at the Childress campus being built for Microsoft.

Confirmed in the source:

What we did: Read our cached copy of the publisher (https://www.abcmoney.co.uk/2026/08/iren-microsoft-ai-deal-clears-first-hurdle-shares-jump-10/) in full (6,759 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms IREN Microsoft AI deal clears first hurdle, shares jump 10% - ABC Money

Quote: “Horizon 1 is the first of four planned 50MW tranches, together making up 200MW”

View cached copy (2026-08-31)Live source ↗