Childress Phase 2-3 adding 200MW
Company: IREN - Project: Childress
What the later record shows
Delivered on time · happened December 31, 2024
Childress Phases 2-3 (upsized to 250MW) were built during H2 2024. The December 2024 update shows 350MW at Childress complete and operating, with total hashrate of 31 EH/s, exceeding the 20 EH/s target.
“4 data center buildings complete, energized and hashing”
2024-12-05 · iren 8-K exhibit (nov2024monthlyupdatevdc.htm) View cached copy (2026-10-24)Live source ↗
“Childress (Texas, USA) 350 21.1 Complete Operating Total Operating 510 31”
2025-01-06 · iren 8-K exhibit (irendec2024monthlyupdate.htm) View cached copy (2026-10-21)Live source ↗
Checked November 15, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Childress Phases 2-3 are expected to add 200MW in H2 2024 and can support expansion to 20 EH/s by end of the year.
Source (primary)
iren 8-K exhibit (ef20018887_ex99-1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-14)Live source ↗
Quote: “Childress project can support expansion to 20 EH/s by end of the year”
How we checked this
Additional evidence
confirms iren 8-K exhibit (ef20018887_ex99-1.htm)
Quote: “Childress project can support expansion to 20 EH/s by end of the year”
confirms iren 8-K exhibit (irendec2024monthlyupdate.htm)
Quote: “Childress (Texas, USA) 350 21.1 Complete Operating Total Operating 510 31”
confirms iren 8-K exhibit (nov2024monthlyupdatevdc.htm)
Quote: “4 data center buildings complete, energized and hashing”