Childress Phase 3 minimum 200 MW data center capacity

Company: IREN

Subject kind
facility capacity
Statement date
2024-10-14
Promised amount
200.0 MW
Current status
stated

The claim, verbatim

Owner agrees its data center facility in the reinvestment zone will have a minimum Data Center Capacity of 200 MW (AC); the abatement is conditioned on capacity not falling below this.

Source (primary)

Childress County TX tax abatement - US IE Hardware- Amended and Restated Phase 3 (Clarendon College) (CHILDRESS_CO_TX, records_response)
View cached copy (2026-10-17)Live source ↗

Quote: “Owner agrees that its data center facility on the Site in the Reinvestment Zone will have a minimum Data Center Capacity of no less than two hundred (200) megawatts (AC).”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms Childress County TX tax abatement - US IE Hardware- Amended and Restated Phase 3 (Clarendon College)

Quote: “Owner agrees that its data center facility on the Site in the Reinvestment Zone will have a minimum Data Center Capacity of no less than two hundred (200) megawatts (AC).”

View cached copy (2026-10-17)Live source ↗