Childress 80MW expansion on track, delivery from early 2024
Company: IREN - Project: Childress
What the later record shows
Delivered on time · happened March 29, 2024
The data centers were delivered progressively from early 2024: 60MW operating by March 29, 85MW by May, and the full 100MW Phase 1 complete by August 2024.
“Childress Phase 1 (first 100MW) – H1 2024 o Supports expansion to 10 EH/s o 60MW operating, 40MW under construction”
2024-04-03 · iren 8-K exhibit (ef20026073_ex99-1.htm) View cached copy (2026-11-08)Live source ↗
“Childress Phase 1 (Texas, USA) 85 4.2 Complete Operating Total Operating 245 9.4”
2024-05-05 · iren 8-K exhibit (ef20028541_ex99-1.htm) View cached copy (2026-11-06)Live source ↗
“Childress Phase 1 (Texas, USA) 100 4.8 Complete Operating”
2024-08-05 · iren 8-K exhibit (irenjuly2024monthlyupdat.htm) View cached copy (2026-10-31)Live source ↗
Checked November 19, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
The 80MW expansion at Childress remains on track. Data centers are expected to be delivered progressively starting in early 2024.
Source (primary)
iren 8-K exhibit (ef20012126_ex99-1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-18)Live source ↗
Quote: “The Company’s 80MW expansion at Childress remains on track, with data centers expected to be delivered progressively from early 2024.”
How we checked this
Checked on November 21, 2026. The cited source supports every part of this claim.
The October 6, 2023 press release states that the 80MW Childress expansion remains on track, with data centers expected to be delivered progressively from early 2024.
Confirmed in the source:
- Iris Energy's 80MW expansion at Childress remains on track (as of October 6, 2023)
- Data centers at Childress are expected to be delivered progressively starting in early 2024
What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1878848/000114036123047243/ef20012126_ex99-1.htm) in full (13,698 characters, retrieved November 18, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms iren 8-K exhibit (ef20012126_ex99-1.htm)
Quote: “The Company’s 80MW expansion at Childress remains on track, with data centers expected to be delivered progressively from early 2024.”
confirms iren 8-K exhibit (irenjuly2024monthlyupdat.htm)
Quote: “Childress Phase 1 (Texas, USA) 100 4.8 Complete Operating”
confirms iren 8-K exhibit (ef20028541_ex99-1.htm)
Quote: “Childress Phase 1 (Texas, USA) 85 4.2 Complete Operating Total Operating 245 9.4”
confirms iren 8-K exhibit (ef20026073_ex99-1.htm)
Quote: “Childress Phase 1 (first 100MW) – H1 2024 o Supports expansion to 10 EH/s o 60MW operating, 40MW under construction”