Childress Phase 1 minimum data center capacity
Company: IREN
The claim, verbatim
The owner agreed that its Childress data center will have a minimum Data Center Capacity of no less than 100 MW AC, and the abatement is conditioned on that minimum.
Source (primary)
Childress County TX tax abatement - US IE Hardware- Phase 1 (CHILDRESS_CO_TX, records_response)
View cached copy (2026-10-17)Live source ↗
Quote: “Owner agrees that its data center facility on the Site in the Reinvestment Zone will have a minimum Data Center Capacity of no less than one hundred (100) megawatts (AC).”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms Childress County TX tax abatement - US IE Hardware- Phase 1
Quote: “Owner agrees that its data center facility on the Site in the Reinvestment Zone will have a minimum Data Center Capacity of no less than one hundred (100) megawatts (AC).”