Childress expansion to 750MW by end-2025
Company: IREN
What the later record shows
Partly delivered
As of June 30, 2025, 650MW of Childress was operating. Horizon 1 (75MW) was under construction and 25MW was only 'power available'. No passage shows 750MW reached by year-end 2025.
“our 750MW Childress site, now supporting 650MW of operating capacity and forming the foundation of our next phase of growth”
2025-06-29 · iren 8-K exhibit (a50ehsupdate_vff.htm) View cached copy (2026-10-11)Live source ↗
“Childress BTC Mining (Texas, USA) 650 40.1 Operating Total Operating 810 50.0 Childress Horizon 1 (Texas, USA) 75 N/A Under construction”
2025-08-27 · IREN 10-K filed 2025-08-28 View cached copy (2026-08-31)Live source ↗
Checked October 20, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
IREN's going-concern forecast assumes Childress installed nameplate capacity reaches 750MW by 31 December 2025.
Source (primary)
iren 8-K exhibit (iren-20241231_d2.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-20)Live source ↗
Quote: “and 750MW by 31 December 2025”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms iren 8-K exhibit (iren-20241231_d2.htm)
Quote: “and 750MW by 31 December 2025”