jain.com

Childress Phase 4 data centers (150MW) hosting new mining hardware

Company: IREN - Project: Childress

Subject kind
facility capacity
Statement date
2025-04-15
Promised amount
150.0 MW
Current status
stated

The claim, verbatim

Additional mining hardware has been commissioned within IREN's 150MW Childress Phase 4 data centers.

Source (primary)

iren 8-K exhibit (pressrelease-40ehsupdate.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-16)Live source ↗

Quote: “following the commissioning of additional mining hardware within its Childress Phase 4 (150MW) data centers”

How we checked this

Checked on October 17, 2026. The cited source supports every part of this claim.

The press release says additional mining hardware was commissioned within IREN's Childress Phase 4 (150MW) data centers.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1878848/000187884825000034/pressrelease-40ehsupdate.htm) in full (14,101 characters, retrieved October 16, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms iren 8-K exhibit (pressrelease-40ehsupdate.htm)

Quote: “following the commissioning of additional mining hardware within its Childress Phase 4 (150MW) data centers”

View cached copy (2026-10-16)Live source ↗