Childress Phase 1 remaining 80MW construction

Company: IREN - Project: Childress

Subject kind
facility timeline
Statement date
2023-09-05
Promised by
2024-03-31
Promised amount
80.0 MW
Current status
verified

What the later record shows

Delivered late · happened June 30, 2024

In March 2024, 40MW of Childress Phase 1 was still under construction with H1 2024 timing. By the July 2024 update and the June 30, 2024 property table, the full 100MW of Phase 1 was complete and operating, after the Q1 2024 target.

“Childress Phase 1 (Texas, USA) 40 3.0 6 H1 2024 Under construction”
2024-03-05 · iren 8-K exhibit (ef20023430_ex99-1.htm) View cached copy (2026-11-09)Live source ↗
“Childress Phase 1 (Texas, USA) 100 4.8 Complete Operating Total Operating 260 10”
2024-07-04 · iren 8-K exhibit (junemonthlyinvestorupdat.htm) View cached copy (2026-11-01)Live source ↗

Checked November 20, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Construction of the remaining 80MW (4 x 20MW data centers) of Childress Phase 1 (first 100MW) remains on track. Mass grading civil works are complete and concrete foundations for the second data center are in progress. Indicative timing for the start of data center delivery is early 2024.

Source (primary)

iren 8-K exhibit (brhc20058546_ex99-1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-20)Live source ↗

Quote: “Construction of the remaining 80MW (4 x 20MW data centers) for Phase 1 (first 100MW) remains on track with mass grading civil works completed, and concrete foundations for the second data center in progress.”

How we checked this

Checked on November 21, 2026. The cited source supports every part of this claim.

The document describes the construction status. Its capacity table lists the 80MW Childress expansion as 'Early 2024', and a footnote defines that date as indicative timing for when data center delivery begins.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1878848/000114036123042844/brhc20058546_ex99-1.htm) in full (16,412 characters, retrieved November 20, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms iren 8-K exhibit (brhc20058546_ex99-1.htm)

Quote: “Construction of the remaining 80MW (4 x 20MW data centers) for Phase 1 (first 100MW) remains on track with mass grading civil works completed, and concrete foundations for the second data center in progress.”

View cached copy (2026-11-20)Live source ↗

confirms iren 8-K exhibit (junemonthlyinvestorupdat.htm)

Quote: “Childress Phase 1 (Texas, USA) 100 4.8 Complete Operating Total Operating 260 10”

View cached copy (2026-11-01)Live source ↗

confirms iren 8-K exhibit (ef20023430_ex99-1.htm)

Quote: “Childress Phase 1 (Texas, USA) 40 3.0 6 H1 2024 Under construction”

View cached copy (2026-11-09)Live source ↗

Record of changes

November 20, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
November 20, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.