Childress Phase 2 (100MW) by 3Q 2024
Company: IREN
What the later record shows
Delivered on time · happened September 30, 2024
In August 2024, 60MW of Phase 2 remained, due September 2024. The September update shows Childress at 200MW 'Complete Operating', which covers Phase 1 (100MW) plus Phase 2 (100MW).
“Childress (Texas, USA) 140 7.3 Complete Operating Total Operating 300 16”
2024-09-04 · iren 8-K exhibit (irenaug2024monthlyupdate.htm) View cached copy (2026-10-29)Live source ↗
“Childress (Texas, USA) 200 11.1 Complete Operating Total Operating 360 21”
2024-10-03 · iren 8-K exhibit (irensepmonthlyupdate4oct.htm) View cached copy (2026-10-26)Live source ↗
Checked November 4, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Childress Phase 2 (100MW, 6 EH/s) is under construction and scheduled for 3Q 2024. Foundations, building structures and electrical works are ongoing.
Source (primary)
iren 8-K exhibit (ef20030723_ex99-1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-04)Live source ↗
Quote: “Childress Phase 2 (100MW) – 3Q 2024”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms iren 8-K exhibit (ef20030723_ex99-1.htm)
Quote: “Childress Phase 2 (100MW) – 3Q 2024”
confirms iren 8-K exhibit (irensepmonthlyupdate4oct.htm)
Quote: “Childress (Texas, USA) 200 11.1 Complete Operating Total Operating 360 21”
confirms iren 8-K exhibit (irenaug2024monthlyupdate.htm)
Quote: “Childress (Texas, USA) 140 7.3 Complete Operating Total Operating 300 16”