Childress Phase 3 (150MW) completion in 4Q 2024
Company: IREN
What the later record shows
Delivered on time · happened December 31, 2024
The December 2024 update states Childress Phase 3 (150MW) was complete, with all six 25MW buildings energized and hashing.
“6 x 25MW data center buildings now complete, energized and hashing”
2025-01-06 · iren 8-K exhibit (irendec2024monthlyupdate.htm) View cached copy (2026-10-21)Live source ↗
“Installed self-mining capacity increased to 31 EH/s during the month following completion of Childress Phase 3”
2025-01-06 · iren 8-K exhibit (irendec2024monthlyupdate.htm) View cached copy (2026-10-21)Live source ↗
Checked October 25, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Childress Phase 3 (150MW, 10 EH/s) is scheduled for 4Q 2024; the substation transformer is installed and building construction and electrical works are ongoing.
Source (primary)
iren 8-K exhibit (irenoctober2024monthlyin.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-25)Live source ↗
Quote: “Childress Phase 3 (150MW): 4Q 2024 o Substation transformer installed o DC building construction and electrical works ongoing”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms iren 8-K exhibit (irenoctober2024monthlyin.htm)
Quote: “Childress Phase 3 (150MW): 4Q 2024 o Substation transformer installed o DC building construction and electrical works ongoing”
confirms iren 8-K exhibit (irendec2024monthlyupdate.htm)
Quote: “6 x 25MW data center buildings now complete, energized and hashing”