Childress 750MW completion by end-2025
Company: IREN
What the later record shows
Partly delivered
Childress had 650MW of the 750MW operating at June 30, 2025. The final 100MW was repurposed into Horizon 1 (75MW, under construction) and a 25MW expansion ('power available'). No passage shows the full 750MW completed.
“Childress BTC Mining (Texas, USA) 650 40.1 Operating Total Operating 810 50.0 Childress Horizon 1 (Texas, USA) 75 N/A Under construction”
2025-08-27 · IREN 10-K filed 2025-08-28 View cached copy (2026-08-31)Live source ↗
“Childress Expansion 25 Power available Sweetwater 2 (Texas, USA) 600 Connection agreement signed”
2025-08-27 · IREN 10-K filed 2025-08-28 View cached copy (2026-08-31)Live source ↗
Checked October 21, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
IREN plans to build the final 100MW (Phase 6) at Childress, completing the full 750MW data center project by the end of 2025.
Source (primary)
iren 8-K exhibit (ny20037451x2_ex99-1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-21)Live source ↗
Quote: “construction of the final 100MW (Phase 6) at Childress, completing the full 750MW data center project by the end of 2025”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms iren 8-K exhibit (ny20037451x2_ex99-1.htm)
Quote: “construction of the final 100MW (Phase 6) at Childress, completing the full 750MW data center project by the end of 2025”