jain.com

Childress operating capacity at 350MW

Company: IREN

Subject kind
facility capacity
Statement date
2024-12-22
Promised amount
350.0 MW
Current status
stated

The claim, verbatim

Childress expanded from 20MW of operating data centers at the start of the year to 350MW following completion of Phase 3.

Source (primary)

iren 8-K exhibit (a31ehannouncement.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-22)Live source ↗

Quote: “Childress now supports 350MW of operating capacity”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms iren 8-K exhibit (a31ehannouncement.htm)

Quote: “Childress now supports 350MW of operating capacity”

View cached copy (2026-10-22)Live source ↗