Childress 80MW expansion delivery timing
Company: IREN - Project: Childress
What the later record shows
Delivered on time · happened March 29, 2024
By March 29, 2024, Childress Phase 1 had 60MW operating, up from the initial 20MW, so delivery began in early 2024. By August 2024 the full 100MW Phase 1 was complete and operating.
“Childress Phase 1 (first 100MW) – H1 2024 o Supports expansion to 10 EH/s o 60MW operating, 40MW under construction”
2024-04-03 · iren 8-K exhibit (ef20026073_ex99-1.htm) View cached copy (2026-11-08)Live source ↗
“Childress Phase 1 (Texas, USA) 100 4.8 Complete Operating”
2024-08-05 · iren 8-K exhibit (irenjuly2024monthlyupdat.htm) View cached copy (2026-10-31)Live source ↗
Checked November 19, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Construction of the remaining 80MW (4 x 20MW data centers) of Childress Phase 1 is on track, with indicative commencement of data center delivery in early 2024.
Source (primary)
iren 8-K exhibit (ef20012021_ex99-1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-18)Live source ↗
Quote: “Childress (Texas, USA) 80 3.5 13 Early 2024 14 Under construction”
How we checked this
Checked on November 21, 2026. The cited source supports every part of this claim.
The update says construction of the remaining 80MW (4 x 20MW data centers) for Childress Phase 1 remains on track. Its site table lists 'Early 2024', which a footnote defines as indicative timing for the start of data center delivery.
Confirmed in the source:
- Construction of the remaining 80MW (4 x 20MW data centers) of Childress Phase 1 is on track
- The 80MW Childress expansion is listed as under construction with timing of Early 2024
- Early 2024 is described as indicative timing for commencement of delivery of the data centers
What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1878848/000114036123047077/ef20012021_ex99-1.htm) in full (23,783 characters, retrieved November 18, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms iren 8-K exhibit (ef20012021_ex99-1.htm)
Quote: “Childress (Texas, USA) 80 3.5 13 Early 2024 14 Under construction”
confirms iren 8-K exhibit (irenjuly2024monthlyupdat.htm)
Quote: “Childress Phase 1 (Texas, USA) 100 4.8 Complete Operating”
confirms iren 8-K exhibit (ef20026073_ex99-1.htm)
Quote: “Childress Phase 1 (first 100MW) – H1 2024 o Supports expansion to 10 EH/s o 60MW operating, 40MW under construction”