Childress Phase 1 ahead of schedule

Company: IREN - Project: Childress

Subject kind
facility timeline
Statement date
2024-01-04
Promised by
2024-01-31
Promised amount
100.0 MW
Current status
verified

What the later record shows

Delivered late · happened June 30, 2024

Delivery of Childress Phase 1 was progressive: 60MW was energized by March 2024 and 85MW was operating in May. The full 100MW was listed as operating as of June 30, 2024, well after the January 2024 date.

“60MW energized, 40MW to be commissioned in the coming months”
2024-03-05 · iren 8-K exhibit (ef20023430_ex99-1.htm) View cached copy (2026-11-09)Live source ↗
“Childress Phase 1 (Texas, USA) 15 0.6 May 2024 Under construction”
2024-05-05 · iren 8-K exhibit (ef20028541_ex99-1.htm) View cached copy (2026-11-06)Live source ↗
“Childress Phase 1 (Texas, USA) 100 4.8 Operating Total Operating 260 10.0”
2024-08-27 · IREN 20-F filed 2024-08-28 View cached copy (2026-08-31)Live source ↗

Checked November 15, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Construction of the remainder of Childress Phase 1 (100MW) is ahead of schedule and on track for progressive delivery from January 2024.

Source (primary)

iren 8-K exhibit (ef20018183_ex99-1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-15)Live source ↗

Quote: “Construction for the remainder of Phase 1 (100MW) is ahead of schedule and on track to be progressively delivered from January 2024”

How we checked this

Attempted on November 17, 2026. We could not read enough of the cited source to check this claim.

The verification run did not return a result for this claim (claude -p exit 1: b'').

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1878848/000114036124000809/ef20018183_ex99-1.htm) in full (19,930 characters, retrieved November 15, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms iren 8-K exhibit (ef20018183_ex99-1.htm)

Quote: “Construction for the remainder of Phase 1 (100MW) is ahead of schedule and on track to be progressively delivered from January 2024”

View cached copy (2026-11-15)Live source ↗

confirms IREN 20-F filed 2024-08-28

Quote: “Childress Phase 1 (Texas, USA) 100 4.8 Operating Total Operating 260 10.0”

View cached copy (2026-08-31)Live source ↗

confirms iren 8-K exhibit (ef20028541_ex99-1.htm)

Quote: “Childress Phase 1 (Texas, USA) 15 0.6 May 2024 Under construction”

View cached copy (2026-11-06)Live source ↗

confirms iren 8-K exhibit (ef20023430_ex99-1.htm)

Quote: “60MW energized, 40MW to be commissioned in the coming months”

View cached copy (2026-11-09)Live source ↗

Record of changes

November 15, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
November 15, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
November 15, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.