Additional 50MW at Childress Phase 3 in 2024

Company: IREN - Project: Childress

Subject kind
facility timeline
Statement date
2024-04-28
Promised by
2024-12-31
Promised amount
50.0 MW
Current status
verified

What the later record shows

Delivered on time · happened December 31, 2024

Childress Phases 1-3 were planned at 100+100+150MW, which includes the extra 50MW. The January 2025 update shows Childress operating at 350MW, and the growth chart places the 510MW total at H2 '24. The passages do not single out the 50MW increment or its exact date.

“Additional 50MW now to be commissioned as part of Childress Phase 3”
2024-05-05 · iren 8-K exhibit (ef20028541_ex99-1.htm) View cached copy (2026-11-06)Live source ↗
“Operating (350MW) | 21.1 EH/s Under Construction H1 2025 (300MW) H2 2025 (100MW) Grid-Connected Power Secured 510MW Operating”
2025-02-05 · iren 8-K exhibit (janmonthlyupdatevff.htm) View cached copy (2026-10-20)Live source ↗

Checked November 8, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

IREN expects to commission an additional 50MW of data center capacity as part of Childress Phase 3 this year, enabled partly by a new substation design.

Source (primary)

iren 8-K exhibit (ef20027927_ex99-1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-08)Live source ↗

Quote: “the Company now expects to commission an additional 50MW of data center capacity as part of Childress Phase 3 this year”

How we checked this

Checked on November 10, 2026. The cited source supports every part of this claim.

IREN's April 29, 2024 release states it expects to commission an additional 50MW at Childress Phase 3 this year and says this was enabled partly through a new substation design.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1878848/000114036124022673/ef20027927_ex99-1.htm) in full (12,180 characters, retrieved November 8, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms iren 8-K exhibit (ef20027927_ex99-1.htm)

Quote: “the Company now expects to commission an additional 50MW of data center capacity as part of Childress Phase 3 this year”

View cached copy (2026-11-08)Live source ↗

confirms iren 8-K exhibit (janmonthlyupdatevff.htm)

Quote: “Operating (350MW) | 21.1 EH/s Under Construction H1 2025 (300MW) H2 2025 (100MW) Grid-Connected Power Secured 510MW Operating”

View cached copy (2026-10-20)Live source ↗

confirms iren 8-K exhibit (ef20028541_ex99-1.htm)

Quote: “Additional 50MW now to be commissioned as part of Childress Phase 3”

View cached copy (2026-11-06)Live source ↗

Record of changes

November 8, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
November 8, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.