Childress Phase 2 minimum 300 MW data center capacity
Company: IREN
The claim, verbatim
Owner agrees its data center facility in the Reinvestment Zone will have a minimum Data Center Capacity of no less than 300 MW (AC); the abatement is conditioned on this minimum.
Source (primary)
Childress County TX tax abatement - US IE Hardware- Amended and Restated Phase 2 (Clarendon College) (CHILDRESS_CO_TX, records_response)
View cached copy (2026-10-17)Live source ↗
Quote: “Owner agrees that its data center facility on the Site in the Reinvestment Zone will have a minimum Data Center Capacity of no less than three hundred (300) megawatts (AC).”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms Childress County TX tax abatement - US IE Hardware- Amended and Restated Phase 2 (Clarendon College)
Quote: “Owner agrees that its data center facility on the Site in the Reinvestment Zone will have a minimum Data Center Capacity of no less than three hundred (300) megawatts (AC).”