jain.com

Childress Phase 2 minimum 300 MW data center capacity

Company: IREN

Subject kind
facility capacity
Statement date
2024-10-14
Promised amount
300.0 MW
Current status
stated

The claim, verbatim

Owner agrees its data center facility in the Reinvestment Zone will have a minimum Data Center Capacity of no less than 300 MW (AC); the abatement is conditioned on this minimum.

Source (primary)

Childress County TX tax abatement - US IE Hardware- Amended and Restated Phase 2 (Clarendon College) (CHILDRESS_CO_TX, records_response)
View cached copy (2026-10-17)Live source ↗

Quote: “Owner agrees that its data center facility on the Site in the Reinvestment Zone will have a minimum Data Center Capacity of no less than three hundred (300) megawatts (AC).”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms Childress County TX tax abatement - US IE Hardware- Amended and Restated Phase 2 (Clarendon College)

Quote: “Owner agrees that its data center facility on the Site in the Reinvestment Zone will have a minimum Data Center Capacity of no less than three hundred (300) megawatts (AC).”

View cached copy (2026-10-17)Live source ↗