Childress Phases 4-5 (300MW) in 2025

Company: IREN

Subject kind
facility timeline
Statement date
2024-11-05
Promised by
2025-12-31
Promised amount
300.0 MW
Current status
verified

What the later record shows

Delivered on time · happened June 30, 2025

Phase 4 was fully operational by April 2025. Phase 5 energization followed, and Childress mining was at 650MW operating as of June 30, 2025, which covers Phases 1-5.

“Childress (750MW) • Phase 1-4 (500MW) now fully operational • Phase 5 (150MW) structures nearing completion”
2025-05-05 · iren 8-K exhibit (aprilmonthlyupdatevf.htm) View cached copy (2026-10-16)Live source ↗
“Childress BTC Mining (Texas, USA) 650 40.1 Operating Total Operating 810 50.0”
2025-08-27 · IREN 10-K filed 2025-08-28 View cached copy (2026-08-31)Live source ↗

Checked October 25, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Childress Phases 4-5 (300MW, 20 EH/s) are under construction with 2025 timing; data center building foundation construction is underway for Phase 4.

Source (primary)

iren 8-K exhibit (irenoctober2024monthlyin.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-25)Live source ↗

Quote: “Childress Phase 4 - 5 (Texas, USA) 300 20 2025 Under construction”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms iren 8-K exhibit (irenoctober2024monthlyin.htm)

Quote: “Childress Phase 4 - 5 (Texas, USA) 300 20 2025 Under construction”

View cached copy (2026-10-25)Live source ↗

confirms IREN 10-K filed 2025-08-28

Quote: “Childress BTC Mining (Texas, USA) 650 40.1 Operating Total Operating 810 50.0”

View cached copy (2026-08-31)Live source ↗

confirms iren 8-K exhibit (aprilmonthlyupdatevf.htm)

Quote: “Childress (750MW) • Phase 1-4 (500MW) now fully operational • Phase 5 (150MW) structures nearing completion”

View cached copy (2026-10-16)Live source ↗

Record of changes

October 25, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 25, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.