Childress Phase 3 150MW in 4Q 2024
Company: IREN
What the later record shows
Delivered on time · happened December 31, 2024
The December 2024 update says all six 25MW Phase 3 buildings were complete, energized and hashing. That is within 4Q 2024.
“6 x 25MW data center buildings now complete, energized and hashing”
2025-01-06 · iren 8-K exhibit (irendec2024monthlyupdate.htm) View cached copy (2026-10-21)Live source ↗
“Installed self-mining capacity increased to 31 EH/s during the month following completion of Childress Phase 3”
2025-01-06 · iren 8-K exhibit (irendec2024monthlyupdate.htm) View cached copy (2026-10-21)Live source ↗
Checked October 29, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Childress Phase 3 (150MW, 6 x 25MW data centers) is under construction with completion targeted for 4Q/December 2024.
Source (primary)
iren 8-K exhibit (irenaug2024monthlyupdate.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-29)Live source ↗
Quote: “Childress Phase 3 (150MW) – 4Q 2024”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms iren 8-K exhibit (irenaug2024monthlyupdate.htm)
Quote: “Childress Phase 3 (150MW) – 4Q 2024”
confirms iren 8-K exhibit (irendec2024monthlyupdate.htm)
Quote: “6 x 25MW data center buildings now complete, energized and hashing”