Childress Phase 2 completion Sep 2024
Company: IREN
What the later record shows
Delivered on time · happened September 30, 2024
The September 2024 monthly update shows Childress at 200MW 'Complete Operating', which would be Phases 1 and 2 at 100MW each. Phase 2 is not named separately.
“Childress (Texas, USA) 200 11.1 Complete Operating Total Operating 360 21”
2024-10-03 · iren 8-K exhibit (irensepmonthlyupdate4oct.htm) View cached copy (2026-10-26)Live source ↗
Checked October 29, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Childress Phase 2 (100MW) is scheduled for completion in September 2024.
Source (primary)
iren 8-K exhibit (irenaug2024monthlyupdate.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-29)Live source ↗
Quote: “Childress Phase 2 (100MW) – Sep 2024”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms iren 8-K exhibit (irenaug2024monthlyupdate.htm)
Quote: “Childress Phase 2 (100MW) – Sep 2024”
confirms iren 8-K exhibit (irensepmonthlyupdate4oct.htm)
Quote: “Childress (Texas, USA) 200 11.1 Complete Operating Total Operating 360 21”