Childress Phase 4-5 (300MW) completion
Company: IREN
What the later record shows
Delivered on time · happened June 29, 2025
Phase 4 was fully operational by May 2025. By 2025-06-29 Childress had 650MW operating, which equals Phases 1–5, so Phase 5 was also done within H1 2025.
“Phase 1-4 (500MW) now fully operational • Phase 5 (150MW) structures nearing completion”
2025-05-05 · iren 8-K exhibit (aprilmonthlyupdatevf.htm) View cached copy (2026-10-16)Live source ↗
“The 50 EH/s milestone is anchored by our 750MW Childress site, now supporting 650MW of operating capacity”
2025-06-29 · iren 8-K exhibit (a50ehsupdate_vff.htm) View cached copy (2026-10-11)Live source ↗
Checked October 21, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Childress Phases 4-5 (300MW, 19 EH/s) are under construction and scheduled for H1 2025 to support the expansion to 50 EH/s.
Source (primary)
iren 8-K exhibit (irendec2024monthlyupdate.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-21)Live source ↗
Quote: “Childress Phase 4 - 5 (Texas, USA) 300 19 H1 2025 Under construction”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms iren 8-K exhibit (irendec2024monthlyupdate.htm)
Quote: “Childress Phase 4 - 5 (Texas, USA) 300 19 H1 2025 Under construction”
confirms iren 8-K exhibit (a50ehsupdate_vff.htm)
Quote: “The 50 EH/s milestone is anchored by our 750MW Childress site, now supporting 650MW of operating capacity”
confirms iren 8-K exhibit (aprilmonthlyupdatevf.htm)
Quote: “Phase 1-4 (500MW) now fully operational • Phase 5 (150MW) structures nearing completion”