Childress Phase 5 (150MW) energization
Company: IREN - Project: Childress
What the later record shows
Delivered on time · happened June 29, 2025
The July 2025 update says Phase 5 (150MW) is now complete, bringing Childress to 650MW. Childress was already at 650MW operating by the June 29 release and as of June 30, 2025, so this was on time.
“650MW total operating data centers, with Phase 5 (150MW) now complete”
2025-07-06 · iren 8-K exhibit (ef20051646_ex99-1.htm) View cached copy (2026-10-11)Live source ↗
“Our 750MW Childress site has been operating since April 2023 and, as of June 30, 2025, has approximately 650MW of operating data center capacity”
2025-08-27 · IREN 10-K filed 2025-08-28 View cached copy (2026-08-31)Live source ↗
Checked October 13, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Childress Phase 5 (150MW) is expected to be energized in the coming weeks, with the site timeline showing H1 2025. The substation transformer is now installed.
Source (primary)
iren 8-K exhibit (ex991may2025monthlyupdat.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-13)Live source ↗
Quote: “Phase 5 (150MW) energization in coming weeks, with substation transformer now installed”
How we checked this
Checked on October 15, 2026. The cited source supports every part of this claim.
The project update says Phase 5 (150MW) energization is coming within weeks with its substation transformer installed, and the site overview lists it as under construction for H1 2025.
Confirmed in the source:
- Childress Phase 5 is 150MW
- Childress Phase 5 energization was expected in the coming weeks
- The site timeline lists the 150MW phase under construction for H1 2025
- The Phase 5 substation transformer is now installed
What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1878848/000187884825000045/ex991may2025monthlyupdat.htm) in full (23,643 characters, retrieved October 13, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms iren 8-K exhibit (ex991may2025monthlyupdat.htm)
Quote: “Phase 5 (150MW) energization in coming weeks, with substation transformer now installed”
confirms IREN 10-K filed 2025-08-28
Quote: “Our 750MW Childress site has been operating since April 2023 and, as of June 30, 2025, has approximately 650MW of operating data center capacity”
confirms iren 8-K exhibit (ef20051646_ex99-1.htm)
Quote: “650MW total operating data centers, with Phase 5 (150MW) now complete”