Childress Phase 5 (150MW) energization

Company: IREN - Project: Childress

Subject kind
facility timeline
Statement date
2025-06-04
Promised by
2025-06-30
Promised amount
150.0 MW
Current status
verified

What the later record shows

Delivered on time · happened June 29, 2025

The July 2025 update says Phase 5 (150MW) is now complete, bringing Childress to 650MW. Childress was already at 650MW operating by the June 29 release and as of June 30, 2025, so this was on time.

“650MW total operating data centers, with Phase 5 (150MW) now complete”
2025-07-06 · iren 8-K exhibit (ef20051646_ex99-1.htm) View cached copy (2026-10-11)Live source ↗
“Our 750MW Childress site has been operating since April 2023 and, as of June 30, 2025, has approximately 650MW of operating data center capacity”
2025-08-27 · IREN 10-K filed 2025-08-28 View cached copy (2026-08-31)Live source ↗

Checked October 13, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Childress Phase 5 (150MW) is expected to be energized in the coming weeks, with the site timeline showing H1 2025. The substation transformer is now installed.

Source (primary)

iren 8-K exhibit (ex991may2025monthlyupdat.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-13)Live source ↗

Quote: “Phase 5 (150MW) energization in coming weeks, with substation transformer now installed”

How we checked this

Checked on October 15, 2026. The cited source supports every part of this claim.

The project update says Phase 5 (150MW) energization is coming within weeks with its substation transformer installed, and the site overview lists it as under construction for H1 2025.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1878848/000187884825000045/ex991may2025monthlyupdat.htm) in full (23,643 characters, retrieved October 13, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms iren 8-K exhibit (ex991may2025monthlyupdat.htm)

Quote: “Phase 5 (150MW) energization in coming weeks, with substation transformer now installed”

View cached copy (2026-10-13)Live source ↗

confirms IREN 10-K filed 2025-08-28

Quote: “Our 750MW Childress site has been operating since April 2023 and, as of June 30, 2025, has approximately 650MW of operating data center capacity”

View cached copy (2026-08-31)Live source ↗

confirms iren 8-K exhibit (ef20051646_ex99-1.htm)

Quote: “650MW total operating data centers, with Phase 5 (150MW) now complete”

View cached copy (2026-10-11)Live source ↗

Record of changes

October 13, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 13, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.