Installed hashrate rose to 35 EH/s after Childress Phase 4

Company: IREN

Subject kind
facility capacity
Statement date
2025-03-30
Current status
stated

The claim, verbatim

Installed Bitcoin mining capacity increased from 31 EH/s to 35 EH/s after Childress Phase 4 was energized.

Source (primary)

iren 8-K exhibit (businessupdatevf.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-18)Live source ↗

Quote: “Installed capacity increased from 31 EH/s to 35 EH/s, following energization of Childress Phase 4.”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms iren 8-K exhibit (businessupdatevf.htm)

Quote: “Installed capacity increased from 31 EH/s to 35 EH/s, following energization of Childress Phase 4.”

View cached copy (2026-10-18)Live source ↗