Childress Commercial Operations deadline

Company: IREN

Subject kind
facility timeline
Statement date
2022-03-14
Promised by
2024-12-31
Current status
verified

What the later record shows

Delivered; the record does not say when

Childress has operated since April 2023, but Commercial Operations under the agreement needs 300 MW installed. That level appears only in the March 31, 2025 figure of 500 MW, so on-time completion by December 31, 2024 cannot be confirmed.

“Our Childress site has been operating since April 2023 and, as of June 30, 2024, has approximately 100 MW of data center capacity”
2025-03-19 · IREN 20-F/A filed 2025-03-20 View cached copy (2026-08-31)Live source ↗
“Our 750MW site in Childress has been operating since April 2023 and, as of March 31, 2025, had 500MW of data center capacity”
2025-05-13 · iren 8-K exhibit (irenlimited-exx994mar2025.htm) View cached copy (2026-10-15)Live source ↗

Checked October 17, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

The Owner agreed that the Childress data center Project will achieve Commercial Operations on or before December 31, 2024.

Source (primary)

Childress County TX tax abatement - US IE Hardware- Phase 2 (CHILDRESS_CO_TX, records_response)
View cached copy (2026-10-17)Live source ↗

Quote: “Owner agrees that the Project shall achieve Commercial Operations on or before December 31, 2024.”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms Childress County TX tax abatement - US IE Hardware- Phase 2

Quote: “Owner agrees that the Project shall achieve Commercial Operations on or before December 31, 2024.”

View cached copy (2026-10-17)Live source ↗

confirms IREN 20-F/A filed 2025-03-20

Quote: “Our Childress site has been operating since April 2023 and, as of June 30, 2024, has approximately 100 MW of data center capacity”

View cached copy (2026-08-31)Live source ↗

confirms iren 8-K exhibit (irenlimited-exx994mar2025.htm)

Quote: “Our 750MW site in Childress has been operating since April 2023 and, as of March 31, 2025, had 500MW of data center capacity”

View cached copy (2026-10-15)Live source ↗

Record of changes

October 17, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 17, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.