Childress Commercial Operations deadline
Company: IREN
What the later record shows
Delivered; the record does not say when
Childress has operated since April 2023, but Commercial Operations under the agreement needs 300 MW installed. That level appears only in the March 31, 2025 figure of 500 MW, so on-time completion by December 31, 2024 cannot be confirmed.
“Our Childress site has been operating since April 2023 and, as of June 30, 2024, has approximately 100 MW of data center capacity”
2025-03-19 · IREN 20-F/A filed 2025-03-20 View cached copy (2026-08-31)Live source ↗
“Our 750MW site in Childress has been operating since April 2023 and, as of March 31, 2025, had 500MW of data center capacity”
2025-05-13 · iren 8-K exhibit (irenlimited-exx994mar2025.htm) View cached copy (2026-10-15)Live source ↗
Checked October 17, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
The Owner agreed that the Childress data center Project will achieve Commercial Operations on or before December 31, 2024.
Source (primary)
Childress County TX tax abatement - US IE Hardware- Phase 2 (CHILDRESS_CO_TX, records_response)
View cached copy (2026-10-17)Live source ↗
Quote: “Owner agrees that the Project shall achieve Commercial Operations on or before December 31, 2024.”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms Childress County TX tax abatement - US IE Hardware- Phase 2
Quote: “Owner agrees that the Project shall achieve Commercial Operations on or before December 31, 2024.”
confirms IREN 20-F/A filed 2025-03-20
Quote: “Our Childress site has been operating since April 2023 and, as of June 30, 2024, has approximately 100 MW of data center capacity”
confirms iren 8-K exhibit (irenlimited-exx994mar2025.htm)
Quote: “Our 750MW site in Childress has been operating since April 2023 and, as of March 31, 2025, had 500MW of data center capacity”