Childress Phase 3 completion
Company: IREN
What the later record shows
Delivered on time · happened December 31, 2024
The December 2024 update says all six 25MW Phase 3 buildings were complete, energized and hashing. It also lists Childress at 350MW as Complete/Operating.
“6 x 25MW data center buildings now complete, energized and hashing”
2025-01-06 · iren 8-K exhibit (irendec2024monthlyupdate.htm) View cached copy (2026-10-21)Live source ↗
“Childress (Texas, USA) 350 21.1 Complete Operating”
2025-01-06 · iren 8-K exhibit (irendec2024monthlyupdate.htm) View cached copy (2026-10-21)Live source ↗
Checked October 24, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
The two remaining Childress Phase 3 data center buildings (50MW still under construction) are expected to be progressively completed in December 2024.
Source (primary)
iren 8-K exhibit (nov2024monthlyupdatevdc.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-24)Live source ↗
Quote: “2 data center buildings remaining with progressive completion expected this month”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms iren 8-K exhibit (nov2024monthlyupdatevdc.htm)
Quote: “2 data center buildings remaining with progressive completion expected this month”
confirms iren 8-K exhibit (irendec2024monthlyupdate.htm)
Quote: “6 x 25MW data center buildings now complete, energized and hashing”