Childress Phase 3 (150MW) by 4Q 2024
Company: IREN
What the later record shows
Delivered on time · happened December 31, 2024
In early December 2024, Phase 3 had 4 of 6 buildings hashing and the rest due that month. The December update shows Childress at 350MW complete and operating (Phases 1-3).
“Phase 3 Substation (150MW) energized • 4 data center buildings complete, energized and hashing • 2 data center buildings remaining with progressive completion expected this month”
2024-12-05 · iren 8-K exhibit (nov2024monthlyupdatevdc.htm) View cached copy (2026-10-24)Live source ↗
“Childress (Texas, USA) 350 21.1 Complete Operating Total Operating 510 31”
2025-01-06 · iren 8-K exhibit (irendec2024monthlyupdate.htm) View cached copy (2026-10-21)Live source ↗
Checked November 4, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Childress Phase 3 (150MW, 10 EH/s) is under construction and scheduled for 4Q 2024. Civil works are underway.
Source (primary)
iren 8-K exhibit (ef20030723_ex99-1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-04)Live source ↗
Quote: “Childress Phase 3 (150MW) – 4Q 2024”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms iren 8-K exhibit (ef20030723_ex99-1.htm)
Quote: “Childress Phase 3 (150MW) – 4Q 2024”
confirms iren 8-K exhibit (irendec2024monthlyupdate.htm)
Quote: “Childress (Texas, USA) 350 21.1 Complete Operating Total Operating 510 31”
confirms iren 8-K exhibit (nov2024monthlyupdatevdc.htm)
Quote: “Phase 3 Substation (150MW) energized • 4 data center buildings complete, energized and hashing • 2 data center buildings remaining with progressive completion expected this month”