Childress Phase 1 expansion lifting capacity from 180MW to 260MW
Company: IREN
What the later record shows
Delivered late · happened May 14, 2024
At March 29, 2024 Childress Phase 1 had 60MW operating and 40MW under construction, with the last 15MW slated for May 2024. By May 14, 2024 IREN reported about 260MW of capacity including 100MW in Texas. That is after the January 2024 date, although the claim only said delivery would start incrementally from January.
“Childress Phase 1 (first 100MW) – H1 2024 o Supports expansion to 10 EH/s o 60MW operating, 40MW under construction”
2024-04-03 · iren 8-K exhibit (ef20026073_ex99-1.htm) View cached copy (2026-11-08)Live source ↗
“Childress Phase 1 (Texas, USA) 15 0.6 May 2024 Under construction”
2024-05-05 · iren 8-K exhibit (ef20028541_ex99-1.htm) View cached copy (2026-11-06)Live source ↗
“As of May 14, 2024, we have approximately 260MW of data center capacity and hashrate capacity of approximately 10 EH/s across our sites in BC (160MW) and Texas (100MW).”
2024-05-14 · iren 8-K exhibit (ef20027345_ex99-4.htm) View cached copy (2026-11-05)Live source ↗
Checked November 17, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
IREN expects to expand data center capacity from 180MW to 260MW, delivered incrementally from January 2024, by building out Childress Phase 1 from 20MW to 100MW.
Source (primary)
iren 8-K exhibit (ef20015071_ex99-1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-16)Live source ↗
Quote: “Expansion from 180MW to 260MW delivered incrementally from January 2024”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms iren 8-K exhibit (ef20015071_ex99-1.htm)
Quote: “Expansion from 180MW to 260MW delivered incrementally from January 2024”
confirms iren 8-K exhibit (ef20027345_ex99-4.htm)
Quote: “As of May 14, 2024, we have approximately 260MW of data center capacity and hashrate capacity of approximately 10 EH/s across our sites in BC (160MW) and Texas (100MW).”
confirms iren 8-K exhibit (ef20028541_ex99-1.htm)
Quote: “Childress Phase 1 (Texas, USA) 15 0.6 May 2024 Under construction”
confirms iren 8-K exhibit (ef20026073_ex99-1.htm)
Quote: “Childress Phase 1 (first 100MW) – H1 2024 o Supports expansion to 10 EH/s o 60MW operating, 40MW under construction”