Childress Phase 2 commercial operations deadline

Company: IREN

Subject kind
facility timeline
Statement date
2024-10-14
Promised by
2025-12-31
Current status
verified

What the later record shows

Delivered on time · happened June 30, 2025

Childress grew from 500 MW to 650 MW operating by June 30, 2025, ahead of the December 31, 2025 deadline. Confidence is medium because no passage ties the Phase 2 abatement site to particular Childress phases.

“Prince George (British Columbia, Canada) 50 3.1 Operating Childress BTC Mining (Texas, USA) 650 40.1 Operating”
2025-08-27 · IREN 10-K filed 2025-08-28 View cached copy (2026-08-31)Live source ↗
“Our 750MW Childress site has been operating since April 2023 and, as of September 30, 2025, has approximately 650MW of operating data center capacity”
2025-11-05 · IREN 10-Q filed 2025-11-06 View cached copy (2026-08-31)Live source ↗

Checked October 17, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Owner agrees the Project shall achieve Commercial Operations on or before December 31, 2025.

Source (primary)

Childress County TX tax abatement - US IE Hardware- Amended and Restated Phase 2 (Clarendon College) (CHILDRESS_CO_TX, records_response)
View cached copy (2026-10-17)Live source ↗

Quote: “Owner agrees that the Project shall achieve Commercial Operations on or before December 31, 2025.”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms Childress County TX tax abatement - US IE Hardware- Amended and Restated Phase 2 (Clarendon College)

Quote: “Owner agrees that the Project shall achieve Commercial Operations on or before December 31, 2025.”

View cached copy (2026-10-17)Live source ↗

confirms Childress County TX tax abatement - US IE Hardware- Amended and Restated Phase 2 (County)

Quote: “Owner agrees that the Project shall achieve Commercial Operations on or before December 31, 2025.”

View cached copy (2026-10-17)Live source ↗

confirms IREN 10-K filed 2025-08-28

Quote: “Prince George (British Columbia, Canada) 50 3.1 Operating Childress BTC Mining (Texas, USA) 650 40.1 Operating”

View cached copy (2026-08-31)Live source ↗

confirms IREN 10-Q filed 2025-11-06

Quote: “Our 750MW Childress site has been operating since April 2023 and, as of September 30, 2025, has approximately 650MW of operating data center capacity”

View cached copy (2026-08-31)Live source ↗

Record of changes

October 17, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 17, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.