Childress expansion to 750MW in H2 2025
Company: IREN
What the later record shows
Partly delivered
Childress reached 650MW of operating capacity by June 2025 and was still about 650MW at September 30, 2025. No passage shows the full 750MW being reached.
“The 50 EH/s milestone is anchored by our 750MW Childress site, now supporting 650MW of operating capacity”
2025-06-29 · iren 8-K exhibit (a50ehsupdate_vff.htm) View cached copy (2026-10-11)Live source ↗
“as of September 30, 2025, has approximately 650MW of operating data center capacity and installed hashrate capacity of approximately 40.1 EH/s”
2025-11-05 · IREN 10-Q filed 2025-11-06 View cached copy (2026-08-31)Live source ↗
Checked October 18, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
IREN targets 750MW of data center capacity at Childress in the second half of 2025.
Source (primary)
iren 8-K exhibit (irenlimited-exx992dec2024x.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-18)Live source ↗
Quote: “and 750MW in the second half of 2025”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms iren 8-K exhibit (irenlimited-exx992dec2024x.htm)
Quote: “and 750MW in the second half of 2025”