Lake Mariner Anthropic AI Factory
Project of TeraWulf
Capacity
What has actually been delivered, against what has been promised. Each figure links to the statement it came from.
| Stage | Capacity | As of | Source |
|---|---|---|---|
| Energized power flowing today | 245 MW | 2026-09-01 | Lake Mariner bitcoin mining capacity |
| Contracted a customer is on the hook | 750 MW | 2025-08-13 | Somerset-Brookings power and infrastructure capacity |
| Under construction | 750 MW | 2026-07-29 | 750 MW AI Factory campus |
| Permitted | -- | ||
| Interconnect approved utility has agreed to deliver | -- | ||
| Interconnect requested in a queue, nothing approved | -- | ||
| Announced a press-release figure | 750 MW | 2026-09-01 | Lake Mariner power availability |
Who has claimed this site
Capacity commitments in the order they were announced. A commitment that ended shows why.
2025-05-08
Core42 - tenant · 72.5 MW · 10-year term source
2025-08-13
Fluidstack - tenant · 450 MW · 10-year term source
2025-08-13
Google - guarantor source
2026-09-01
New York Power Authority - offtaker · 90 MW source
2026-09-01
Core42 - guarantor source
Claims about this project
2024-10-09 - stated
20 million shares issued to Riesling Power 20.0 shares.
2024-10-09 - stated
Somerset facility size: 157 acres 157.0 acres.
2024-10-09 - stated
2024-10-09 - stated
Board observer rights for Somerset 15.0 shares.
2024-10-09 - stated
Annual lease rent for Somerset Premises 281398.2 USD.
2024-10-09 - stated
2024-10-09 - stated
2024-10-09 - stated
35-year lease in Somerset, New York 35.0 years.
2025-10-13 - stated
Senior secured notes offering 3200000000.0 USD.
2025-10-13 - stated
Senior secured notes offering 3.2 USD.
2025-10-15 - delayed
2025-10-22 - stated
2025-10-22 - stated
2025-10-22 - stated
2026-02-26 - stated
2026-02-26 - stated
2026-02-26 - stated
2026-02-26 - stated
2026-02-26 - stated
2026-02-26 - stated
2026-04-13 - stated
Lake Mariner expansion capacity targets 500.0 MW.
2026-04-13 - stated
2026-04-13 - stated
2026-04-13 - stated
2026-04-14 - stated
2026-04-14 - stated
Lake Mariner expansion capacity target 500.0 MW.
2026-04-14 - stated
Lake Mariner contracted HPC capacity 438.0 MW.
2026-04-15 - stated
La Lupa and Akela contracted capacity 438.0 MW.
2026-04-15 - stated
2026-04-15 - stated
Lake Mariner expansion capacity 500.0 MW.
2026-07-09 - stated
Anthropic 20-year lease 20 years.
2026-07-13 - stated
$3.5B financing for Anthropic-leased data center 3500000000 USD.
2026-07-15 - revised
2026-07-29 - stated
750 MW AI Factory campus 750.0 MW.
2026-08-03 - stated
2026-08-21 - stated
Lake Mariner operating capacity 102.0 MW.
2026-08-21 - stated
Lake Mariner under-construction capacity 336.0 MW.
2026-08-21 - stated
Lake Mariner capacity under construction 336.0 MW.
2026-08-21 - stated
2026-08-24 - stated
2026-08-24 - stated
2026-08-24 - stated
2026-08-24 - stated
Lake Mariner capacity under construction 336.0 MW.
2026-08-24 - stated
Lake Mariner capacity under construction 336.0 MW.
2026-08-24 - stated
2026-08-31 - stated
Fluidstack Lake Mariner partnership 8700000000.0 USD.
2026-09-01 - delayed
WULF Den Revenue. Promised by 2025-07-31.
2026-09-01 - stated
2026-09-01 - stated
Lake Mariner Lease Amendments 500.0 USD.
2026-09-01 - stated
2026-09-01 - delayed
2026-09-01 - stated
2026-09-01 - stated
Lake Mariner expansion 162.0 MW.
2026-09-01 - stated
2026-09-01 - stated
2026-09-01 - delayed
CB-1 Revenue. Promised by 2025-08-15.
2026-09-01 - stated
Core42 lease at Lake Mariner 72.5 MW.
2026-09-01 - delayed
CB-2 delivery timeline. Promised by 2025-12-31.
2026-09-01 - delayed
CB-2 Delivery. Promised by 2025-12-31.
2026-09-01 - delayed
WULF Den Operational. Promised by 2025-06-30.
2026-09-01 - delayed
2026-09-01 - stated
2026-09-01 - delayed
HPC Project Financing Execution. Promised by 2025-07-01.
2026-09-01 - delayed
2026-09-01 - stated
2026-09-01 - stated
Core42 HPC Data Center Lease 60.0 MW.
2026-09-01 - delayed
2026-09-01 - stated
Bitcoin mining fleet size and composition 54100.0 units.
2026-09-01 - stated
NYPA long-term power allocation 90.0 MW.
2026-09-01 - stated
Lake Mariner HPC capacity energized 18.0 MW.
2026-09-01 - stated
2026-09-01 - stated
2026-09-01 - stated
2026-09-01 - stated
2026-09-01 - stated
2026-09-01 - stated
2026-09-01 - stated
2026-09-01 - delayed
2026-09-01 - delayed
2026-09-01 - stated
2026-09-01 - delayed
CB-2 data center online. Promised by 2025-12-31.
2026-09-01 - stated
Lake Mariner power availability 750.0 MW.
2026-09-01 - stated
2026-09-01 - stated
Fluidstack 10-year leases. Promised by 2035-08-18.
2026-09-01 - delayed
2026-09-01 - stated
Lake Mariner bitcoin mining capacity 245.0 MW.
2026-09-01 - delayed
2026-09-01 - delayed
Long-term HPC datacenter lease agreements. Promised by 2024-12-01.
2026-09-01 - delayed
2026-09-01 - delayed
2026-09-01 - delayed
2026-09-01 - stated
Future capacity expansion design 250.0 MW.
2026-09-01 - delayed
2026-09-01 - stated
2026-09-01 - stated
Beyond 2026 HPC Expansion Potential 250.0 MW.
2026-09-01 - stated
2026-09-01 - stated
Lake Mariner facility expansion target 500.0 MW.
2026-09-01 - stated
Project financing assumption for CB-1 and CB-2 70.0 percent.
2026-09-01 - stated
HPC revenue prepayment assumption 1.5 million USD per MW.
2026-09-01 - delayed