Lake Mariner Fluidstack full 200+ MW by YE 2026

Company: TeraWulf - Project: Lake Mariner Anthropic AI Factory

Subject kind
facility timeline
Statement date
2025-08-13
Promised by
2026-12-31
Promised amount
200.0 MW
Current status
stated

The claim, verbatim

The full 200+ MW of critical IT load for Fluidstack is expected to be deployed by year-end 2026.

Source (primary)

terawulf 8-K exhibit (tm2523008d2_ex99-1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-06)Live source ↗

Quote: “with the full 200+ MW deployed by year-end 2026”

How we checked this

Checked on October 8, 2026. The cited source supports every part of this claim.

The release says the full 200+ MW is expected to be deployed by year-end 2026, delivering capacity to Fluidstack.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1083301/000110465925078084/tm2523008d2_ex99-1.htm) in full (10,293 characters, retrieved October 6, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms terawulf 8-K exhibit (tm2523008d2_ex99-1.htm)

Quote: “with the full 200+ MW deployed by year-end 2026”

View cached copy (2026-10-06)Live source ↗