Core42 72.5 MW lease

Company: TeraWulf - Project: Lake Mariner Anthropic AI Factory

Subject kind
customer
Statement date
2025-08-14
Promised by
2025-12-31
Promised amount
72.5 MW
Current status
verified

What the later record shows

Delivered late · happened March 31, 2026

The Core42 capacity (72.5 MW gross / 60 MW critical IT) was only 18 MW online at 2025 year-end. It was fully energized and generating revenue by March 31, 2026.

“as of December 31, 2025 the Lake Mariner Data Campus operated 245 MW of legacy bitcoin mining capacity and had 18 critical IT MW of HPC capacity”
2026-02-27 · View 10-K PDF View cached copy (2026-09-01)Live source ↗Archive.org ↗
“60 MW of critical IT capacity energized and generating revenue as of March 31, 2026.”
2026-05-07 · terawulf 8-K exhibit (a_wulfearningsreleaseq1202.htm) View cached copy (2026-09-08)Live source ↗

Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Core42 leases 72.5 MW of gross HPC hosting capacity at Lake Mariner in 2025.

Source (primary)

Q2 Earnings Update Presentation (IR page (investors.terawulf.com), ir_presentation)
View cached copy (2026-10-06)Live source ↗

Quote: “Core42: 72.5 MW in 2025”

How we checked this

Checked on October 13, 2026. The cited source supports every part of this claim.

The document lists a Core42 lease for 72.5 MW at Lake Mariner, describes it as 72.5 MW of gross contracted HPC hosting capacity, and shows Core42 at 72.5 MW in 2025 in its capacity overview.

Confirmed in the source:

What we did: Read our cached copy of IR page (investors.terawulf.com) (https://d1io3yog0oux5.cloudfront.net/_26c9692236622f11a71632d61560402c/terawulf/db/2396/23302/pdf/WULF_Q2_2025_Investor_Update_%28Aug_2025%29vF.pdf) in full (17,599 characters, retrieved October 6, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Q2 Earnings Update Presentation

Quote: “Core42: 72.5 MW in 2025”

View cached copy (2026-10-06)Live source ↗

confirms View 10-K PDF

Quote: “as of December 31, 2025 the Lake Mariner Data Campus operated 245 MW of legacy bitcoin mining capacity and had 18 critical IT MW of HPC capacity”

View cached copy (2026-09-01)Live source ↗Archive.org ↗

confirms terawulf 8-K exhibit (a_wulfearningsreleaseq1202.htm)

Quote: “60 MW of critical IT capacity energized and generating revenue as of March 31, 2026.”

View cached copy (2026-09-08)Live source ↗

Record of changes

October 6, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 7, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Review. statement_date 2026-10-06 was the source's retrieval date; source published 2025-08-14.