CB-2 HPC facility operational launch

Company: TeraWulf - Project: Lake Mariner Anthropic AI Factory

This claim was marked delayed on October 9, 2026. Recorded automatically from the cited source when it was published, then queued for evidence review.

How this was decided: Automated extraction from the cited source. The claim is preserved below exactly as it was originally published, so the record shows what was asserted as well as what became of it.

Subject kind
facility timeline
Statement date
2024-10-03
Promised by
2025-06-30
Promised amount
50.0 MW
Current status
delayed

What the later record shows

The date slipped · new target December 31, 2025

CB-2 was due in Q2 2025. In August 2025 the company said it was 'on track for Q4 delivery', which pushes the date to Q4 2025. No passage confirms that it was completed.

“✓ CB-2 on track for Q4 delivery ✓ 10-year, $3.7Bn hyperscale lease with Fluidstack”
2025-08-14 · Q2 Earnings Update Presentation View cached copy (2026-09-01)Live source ↗

Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

CB-2 with 50 MW capacity expected to be operational in Q2 2025

Source (primary)

Nautilus Sale Announcement (IR page (investors.terawulf.com), ir_presentation)
View cached copy (2026-09-01)Live source ↗Archive.org ↗

Quote: “CB-2: 50 MW expected to be operational in Q2 2025”

How we checked this

Checked on October 10, 2026. The cited source supports every part of this claim.

The HPC timeline slide states that CB-2's 50 MW is expected to be operational in Q2 2025.

Confirmed in the source:

What we did: Read our cached copy of IR page (investors.terawulf.com) (https://d1io3yog0oux5.cloudfront.net/_0c87b48cb4d1c6967968c7d0c3e5933d/terawulf/db/2396/23300/pdf/WULF_Nautilus_Sale_Announcement_Deck_%2810-03-24%29vF.pdf) in full (14,394 characters, retrieved September 1, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Nautilus Sale Announcement

Quote: “CB-2: 50 MW expected to be operational in Q2 2025”

View cached copy (2026-09-01)Live source ↗Archive.org ↗

delays Q2 Earnings Update Presentation

Quote: “✓ CB-2 on track for Q4 delivery ✓ 10-year, $3.7Bn hyperscale lease with Fluidstack”

View cached copy (2026-09-01)Live source ↗

Record of changes

September 2, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 2, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Review. statement_date 2026-09-01 was the source's retrieval date; source published 2024-10-03.
October 9, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.