CB4 Lake Mariner commissioning

Company: TeraWulf - Project: Lake Mariner Anthropic AI Factory

Subject kind
facility timeline
Statement date
2026-09-15
Promised by
2026-09-30
Current status
outcome unconfirmed

What the later record shows

The date slipped

No passage confirms CB-4 initial delivery by late September. An October 3 profile still lists the CB-4/CB-5 capacity (336 MW) as under construction.

“Another 336 MW of critical IT capacity is under construction at Lake Mariner through CB-4 and CB-5.”
2026-09-22 · Rothschild Redburn starts TeraWulf at Neutral, $15 target implies 11.8% downside - Yahoo Finance View cached copy (2026-09-29)Live source ↗
“TeraWulf operates the Lake Mariner Data Campus in New York with 102 MW of revenue-generating critical IT capacity and 336 MW under construction”
2026-10-03 · Terawulf (WULF) Stock Price, News & Analysis - 24/7 Wall St. View cached copy (2026-10-08)Live source ↗Archive.org ↗

Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

CB4 at Lake Mariner is in commissioning and on track for initial delivery in late September

Source (primary)

TeraWulf Falls 5% as AI Infrastructure Names Extend a Month-Long Slide; IREN Drops 4%, Applied Digital Declines 3% - Yahoo Finance (-, news_article)
View cached copy (2026-09-18)Live source ↗

Quote: “CB4, which management said 'is in commissioning and remains on track for initial delivery in late September.'”

How we checked this

Checked on October 11, 2026. The cited source supports every part of this claim.

The article quotes management saying CB4 at Lake Mariner is in commissioning and on track for initial delivery in late September.

Confirmed in the source:

What we did: Read our cached copy of the publisher (https://finance.yahoo.com/markets/stocks/articles/terawulf-falls-5-ai-infrastructure-153049003.html) in full (13,054 characters, retrieved September 18, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms TeraWulf Falls 5% as AI Infrastructure Names Extend a Month-Long Slide; IREN Drops 4%, Applied Digital Declines 3% - Yahoo Finance

Quote: “CB4, which management said 'is in commissioning and remains on track for initial delivery in late September.'”

View cached copy (2026-09-18)Live source ↗

confirms TeraWulf Falls 5% as AI Infrastructure Names Extend a Month-Long Slide; IREN Drops 4%, Applied Digital Declines 3% - AOL.com

Quote: “is in commissioning and remains on track for initial delivery in late September”

View cached copy (2026-09-18)Live source ↗

confirms TeraWulf Falls 5% as AI Infrastructure Names Extend a Month-Long Slide; IREN Drops 4%, Applied Digital Declines 3% - 24/7 Wall St.

Quote: “TeraWulf's next hard milestone at Lake Mariner is CB4, which management said "is in commissioning and remains on track for initial delivery in late September."”

View cached copy (2026-09-19)Live source ↗

delays Rothschild Redburn starts TeraWulf at Neutral, $15 target implies 11.8% downside - Yahoo Finance

Quote: “Another 336 MW of critical IT capacity is under construction at Lake Mariner through CB-4 and CB-5.”

View cached copy (2026-09-29)Live source ↗

delays Terawulf (WULF) Stock Price, News & Analysis - 24/7 Wall St.

Quote: “TeraWulf operates the Lake Mariner Data Campus in New York with 102 MW of revenue-generating critical IT capacity and 336 MW under construction”

View cached copy (2026-10-08)Live source ↗Archive.org ↗

Record of changes

September 18, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 1, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.