Fluidstack delivery 40 MW 2H25, 200+ MW by 2H26

Company: TeraWulf - Project: Lake Mariner Anthropic AI Factory

Subject kind
facility timeline
Statement date
2025-08-13
Promised by
2026-12-31
Promised amount
200.0 MW
Current status
stated

The claim, verbatim

Cumulative Fluidstack delivery timeline targets 42 MW in 2H 2025 and 200+ MW in 1H/2H 2026 at Lake Mariner.

Source (primary)

terawulf 8-K exhibit (tm2523008d1_ex99-3.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-06)Live source ↗

Quote: “Cumulative Delivery Timeline 2H 2025 1H 2026 2H 2026 42 MW 200+ MW 20 0+ MW at Lake Mariner”

How we checked this

Checked on October 8, 2026. The cited source supports every part of this claim.

The Fluidstack slide shows a cumulative delivery timeline of 42 MW in 2H 2025 and 200+ MW in 1H and 2H 2026 at Lake Mariner.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1083301/000110465925078086/tm2523008d1_ex99-3.htm) in full (18,636 characters, retrieved October 6, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms terawulf 8-K exhibit (tm2523008d1_ex99-3.htm)

Quote: “Cumulative Delivery Timeline 2H 2025 1H 2026 2H 2026 42 MW 200+ MW 20 0+ MW at Lake Mariner”

View cached copy (2026-10-06)Live source ↗