CB-2 delivery timeline

Company: TeraWulf - Project: Lake Mariner Anthropic AI Factory

Subject kind
facility timeline
Statement date
2025-09-04
Promised by
2025-12-31
Current status
verified

What the later record shows

Delivered late · happened March 31, 2026

Only 18 MW (WULF Den + CB-1) was online at 2025 year-end, so CB-2 missed Q4 2025. CB-2A was online by February 2026 (39 MW) and CB-2B was listed as delivered as of March 31, 2026.

“with 39 critical IT MW HPC capacity online, more than 500 MW of near-term contracted campus capacity”
2026-02-25 · terawulf 8-K exhibit (a_wulfearningsrelease2026-.htm) View cached copy (2026-09-13)Live source ↗
“as of December 31, 2025 the Lake Mariner Data Campus operated 245 MW of legacy bitcoin mining capacity and had 18 critical IT MW of HPC capacity”
2026-02-27 · View 10-K PDF View cached copy (2026-09-01)Live source ↗Archive.org ↗
“WULF Den (2 MW) ➢ CB-1 (16 MW) ➢ CB-2A (21 MW) ➢ CB-2B (21 MW) DELIVERED TO DATE(1)”
2026-05-07 · terawulf 8-K exhibit (terawulfq12026investorpr.htm) View cached copy (2026-09-08)Live source ↗

Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

CB-2 on track for Q4 2025 delivery

Source (primary)

WULF Expands Fluidstack Deal (IR page (investors.terawulf.com), ir_release)
View cached copy (2026-09-01)Live source ↗Archive.org ↗

Quote: “CB-2 on track for Q4 delivery”

How we checked this

Checked on October 10, 2026. The cited source supports part of this claim, but not all of it.

The document says CB-2 is on track for Q4 delivery but does not name the year. The August 2025 date of the presentation suggests 2025, but the document never states it.

Confirmed in the source:

We could not confirm this from the cited source:

That does not mean it is false — only that this source does not establish it, as of the date above. If we find a source that settles it, we will re-check and update this page.

What we did: Read our cached copy of IR page (investors.terawulf.com) (https://d1io3yog0oux5.cloudfront.net/_0c87b48cb4d1c6967968c7d0c3e5933d/terawulf/db/2396/23304/pdf/WULF_Expands_Fluidstack_Deal_August_2025.pdf) in full (11,936 characters, retrieved September 1, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms WULF Expands Fluidstack Deal

Quote: “CB-2 on track for Q4 delivery”

View cached copy (2026-09-01)Live source ↗Archive.org ↗

confirms View 10-K PDF

Quote: “as of December 31, 2025 the Lake Mariner Data Campus operated 245 MW of legacy bitcoin mining capacity and had 18 critical IT MW of HPC capacity”

View cached copy (2026-09-01)Live source ↗Archive.org ↗

confirms terawulf 8-K exhibit (terawulfq12026investorpr.htm)

Quote: “WULF Den (2 MW) ➢ CB-1 (16 MW) ➢ CB-2A (21 MW) ➢ CB-2B (21 MW) DELIVERED TO DATE(1)”

View cached copy (2026-09-08)Live source ↗

confirms terawulf 8-K exhibit (a_wulfearningsrelease2026-.htm)

Quote: “with 39 critical IT MW HPC capacity online, more than 500 MW of near-term contracted campus capacity”

View cached copy (2026-09-13)Live source ↗

Record of changes

September 2, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 2, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Review. statement_date 2026-09-01 was the source's retrieval date; source published 2025-09-04.
October 9, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.