CB-2 50 MW HPC delivery Q2 2025
Company: TeraWulf
What the later record shows
The date slipped · new target December 31, 2025
CB-2 was promised for Q2 2025, but an August 2025 company presentation said it was 'on track for Q4 delivery', so the date moved to Q4 2025. No later passage names CB-2 as completed. Core42 capacity was delivered through March 2026, but no passage ties CB-2 to it.
“CB - 1 will begin recording revenue mid - August x CB - 2 on track for Q4 delivery”
2025-08-13 · terawulf 8-K exhibit (tm2523008d1_ex99-3.htm) View cached copy (2026-10-06)Live source ↗
“Contract #1 Contracted Delivery Customer Contract #2 Contracted Delivery Customer 60 MW Jul ’25 – Mar ’26”
2026-08-04 · Q2 2026 Earnings Update Presentation View cached copy (2026-10-06)Live source ↗Archive.org ↗
Checked October 25, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
CB-2 (50 MW) HPC data center is scheduled for delivery in Q2 2025.
Source (primary)
terawulf 8-K exhibit (wulfq32024investorpres11.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-25)Live source ↗
Quote: “CB-2 (50 MW) is scheduled for delivery in Q2 2025”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms terawulf 8-K exhibit (wulfq32024investorpres11.htm)
Quote: “CB-2 (50 MW) is scheduled for delivery in Q2 2025”
delays terawulf 8-K exhibit (tm2523008d1_ex99-3.htm)
Quote: “CB - 1 will begin recording revenue mid - August x CB - 2 on track for Q4 delivery”
delays Q2 2026 Earnings Update Presentation
Quote: “Contract #1 Contracted Delivery Customer Contract #2 Contracted Delivery Customer 60 MW Jul ’25 – Mar ’26”