Lake Mariner permanent substation feed

Company: TeraWulf

Subject kind
facility timeline
Statement date
2023-11-01
Current status
stated

The claim, verbatim

Lake Mariner took a planned outage starting October 2 to move from a temporary substation feed to a permanent feed. About 1.4 EH/s was offline for 4.25 days, and the site returned to full operations on October 6.

Source (primary)

terawulf 8-K exhibit (pr-wulfoct23opsreportfinal.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-17)Live source ↗

Quote: “On October 2, Lake Mariner entered a planned outage to transition from a temporary substation feed to a permanent feed. During the outage, approximately 1.4 EH was offline for 4.25 days. Lake Mariner returned to full operations on October 6”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms terawulf 8-K exhibit (pr-wulfoct23opsreportfinal.htm)

Quote: “On October 2, Lake Mariner entered a planned outage to transition from a temporary substation feed to a permanent feed. During the outage, approximately 1.4 EH was offline for 4.25 days. Lake Mariner returned to full operations on October 6”

View cached copy (2026-11-17)Live source ↗