CB-3 data center completion (42 MW critical IT)

Company: TeraWulf - Project: Lake Mariner Anthropic AI Factory

Subject kind
facility timeline
Statement date
2026-05-07
Promised by
2026-05-31
Promised amount
42.0 MW
Current status
verified

What the later record shows

Delivered late · happened July 31, 2026

CB-3 was not fully complete by the end of May: only 81 MW (60 Core42 plus about 21 of CB-3) was energized at June 30. The Q2 deck lists CB-3 (42 MW) as delivered, with 102 MW energized as of July 2026.

“As of June 30, 2026, TeraWulf had energized 81 critical IT MW of HPC leasing capacity at the Lake Mariner Data Campus.”
2026-08-04 · TeraWulf 10-Q filed 2026-08-05 View cached copy (2026-08-31)Live source ↗
“DELIVERED 102 MW ➢ WULF Den (2 MW) ➢ CB - 1 (16 MW) ➢ CB - 2A (21 MW) ➢ CB - 2B (21 MW) ➢ CB - 3 (42 MW)”
2026-08-04 · Q2 2026 Earnings Update Presentation View cached copy (2026-09-01)Live source ↗Archive.org ↗

Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

CB-3 building (42 MW critical IT capacity) is on track for completion in May 2026

Source (primary)

terawulf 8-K exhibit (terawulfq12026investorpr.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-09-08)Live source ↗

Quote: “CB-3 on track for completion”

How we checked this

Checked on October 10, 2026. The cited source supports every part of this claim.

The presentation states 'CB-3 on track for completion' on its 2026 execution slide and lists CB-3 as under construction at 42 MW critical IT with a May timing.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1083301/000108330126000083/terawulfq12026investorpr.htm) in full (27,664 characters, retrieved September 8, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms terawulf 8-K exhibit (terawulfq12026investorpr.htm)

Quote: “CB-3 on track for completion”

View cached copy (2026-09-08)Live source ↗

confirms TeraWulf 10-Q filed 2026-08-05

Quote: “As of June 30, 2026, TeraWulf had energized 81 critical IT MW of HPC leasing capacity at the Lake Mariner Data Campus.”

View cached copy (2026-08-31)Live source ↗

confirms Q2 2026 Earnings Update Presentation

Quote: “DELIVERED 102 MW ➢ WULF Den (2 MW) ➢ CB - 1 (16 MW) ➢ CB - 2A (21 MW) ➢ CB - 2B (21 MW) ➢ CB - 3 (42 MW)”

View cached copy (2026-09-01)Live source ↗Archive.org ↗

Record of changes

September 8, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 9, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.