Lake Mariner CB-5 initial energization

Company: TeraWulf - Project: Lake Mariner Anthropic AI Factory

Subject kind
facility timeline
Statement date
2026-09-16
Promised by
2027-01-15
Promised amount
42.0 MW
Current status
stated

The claim, verbatim

Management expects initial energization of the first 42 megawatt hall in CB-5 in early January 2027, with subsequent halls following in February, March, and April 2027.

Source (primary)

WULF Stock Forecast 2030: TeraWulf Model & Cash Flow - Northwise (-, news_article)
View cached copy (2026-09-20)Live source ↗

Quote: “initial CB-5 energization in early January”

How we checked this

Checked on September 24, 2026. The cited source supports part of this claim, but not all of it.

Only the early-January initial CB-5 energization is a management milestone. The February to April dates are Northwise rent-start assumptions, not management's energization expectations.

Confirmed in the source:

We could not confirm this from the cited source:

That does not mean it is false — only that this source does not establish it, as of the date above. If we find a source that settles it, we will re-check and update this page.

What we did: Read our cached copy of the publisher (https://northwiseproject.com/research/wulf-stock-forecast-2030) in full (77,288 characters, retrieved September 20, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms WULF Stock Forecast 2030: TeraWulf Model & Cash Flow - Northwise

Quote: “initial CB-5 energization in early January”

View cached copy (2026-09-20)Live source ↗