Promised amount
245.0 MW
Current status
stated

The claim, verbatim

As of December 31, 2025, Lake Mariner Data Campus operated 245 MW of legacy bitcoin mining capacity

Source (primary)

View 10-K PDF (IR page (investors.terawulf.com), ir_release)
View cached copy (2026-09-01)Live source ↗Archive.org ↗

Quote: “As of December 31, 2025 the Lake Mariner Data Campus operated 245 MW of legacy bitcoin mining capacity”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms View 10-K PDF

Quote: “As of December 31, 2025 the Lake Mariner Data Campus operated 245 MW of legacy bitcoin mining capacity”