jain.com

Somerset facility size: 157 acres

Company: TeraWulf - Project: Lake Mariner Anthropic AI Factory

Subject kind
facility capacity
Statement date
2024-10-09
Promised amount
157.0 acres
Current status
stated

The claim, verbatim

Lease covers approximately 157 acres for cryptocurrency mining and high-performance computing data center operations

Source (primary)

TeraWulf 8-K filed 2024-10-10 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗

Quote: “for a portion of Somerset's real property located in the Town of Somerset, New York, consisting of approximately 157 acres”

How we checked this

Checked on September 17, 2026. The cited source supports every part of this claim.

The filing gives the 157-acre size and states the Premises will be used for crypto mining and HPC data center operations.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1083301/000108330124000136/wulf-20241009.htm) in full (12,787 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms TeraWulf 8-K filed 2024-10-10

Quote: “for a portion of Somerset's real property located in the Town of Somerset, New York, consisting of approximately 157 acres”

View cached copy (2026-08-31)Live source ↗