Lake Mariner mining capacity expansion to Q2 2023

Company: TeraWulf - Project: Lake Mariner Anthropic AI Factory

Subject kind
facility capacity
Statement date
2023-03-30
Promised by
2023-06-30
Promised amount
110.0 MW
Current status
verified

What the later record shows

Delivered; the record does not say when

By December 31, 2023 Lake Mariner had 33,100 operational miners, near the ~34,000 target, and by March 31, 2024 it had 160 MW energized. No passage states the capacity reached at June 30, 2023, so on-time delivery cannot be confirmed.

“comprised of 33,100 operational miners at the Lake Mariner Facility (including 4,800 hosted miners)”
2024-03-21 · TeraWulf S-3/A filed 2024-03-22 View cached copy (2026-09-13)Live source ↗
“as of March 31, 2024, the Company has energized three buildings and additional infrastructure comprising 160 MW of capacity”
2024-05-12 · TeraWulf 10-Q filed 2024-05-13 View cached copy (2026-09-13)Live source ↗

Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

TeraWulf expects to reach 110 MW of mining capacity at Lake Mariner Facility, representing approximately 34,000 miners, in Q2 2023 pending Building 2 construction completion.

Source (primary)

TeraWulf 10-K filed 2023-03-31 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗

Quote: “TeraWulf expects to reach 110 MW of mining capacity at the facility, representing approximately 34,000 miners, in the second quarter of 2023 pending the completion of construction of Building 2”

How we checked this

Checked on October 11, 2026. The cited source supports every part of this claim.

The Lake Mariner section of the 10-K states this expectation, including the dependence on finishing Building 2.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1083301/000155837023005301/wulf-20221231x10k.htm) in full (569,235 characters, retrieved September 13, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms TeraWulf 10-K filed 2023-03-31

Quote: “TeraWulf expects to reach 110 MW of mining capacity at the facility, representing approximately 34,000 miners, in the second quarter of 2023 pending the completion of construction of Building 2”

View cached copy (2026-09-13)Live source ↗

confirms TeraWulf 10-Q filed 2024-05-13

Quote: “as of March 31, 2024, the Company has energized three buildings and additional infrastructure comprising 160 MW of capacity”

View cached copy (2026-09-13)Live source ↗

confirms TeraWulf S-3/A filed 2024-03-22

Quote: “comprised of 33,100 operational miners at the Lake Mariner Facility (including 4,800 hosted miners)”

View cached copy (2026-09-13)Live source ↗

Record of changes

September 13, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 14, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.