CB-1 HPC facility operational launch
Company: TeraWulf - Project: Lake Mariner Anthropic AI Factory
What the later record shows
The date slipped
As of May 2025, HPC capacity at Lake Mariner was still being developed and expected online 'throughout 2025', and HPC leasing operations only commenced in July 2025. CB-1 is not named in any passage, so its own completion date is unconfirmed.
“supporting up to 72.5 MW of data center infrastructure dedicated to GPU compute workloads. This capacity is expected to come online throughout 2025.”
2025-05-08 · TeraWulf 10-Q filed 2025-05-09 View cached copy (2026-08-31)Live source ↗
“The Company commenced HPC leasing operations at the Lake Mariner Data Campus in July 2025”
2026-02-27 · View 10-K PDF View cached copy (2026-09-01)Live source ↗Archive.org ↗
Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
CB-1 with 20 MW capacity expected to be operational in Q1 2025
Source (primary)
Nautilus Sale Announcement (IR page (investors.terawulf.com), ir_presentation)
View cached copy (2026-09-01)Live source ↗Archive.org ↗
Quote: “CB-1: 20 MW capacity expected to be operational in Q1 2025”
How we checked this
Checked on October 10, 2026. The cited source supports every part of this claim.
The HPC timeline slide states that CB-1's 20 MW capacity is expected to be operational in Q1 2025.
Confirmed in the source:
- CB-1 has 20 MW capacity
- CB-1 is expected to be operational in Q1 2025
What we did: Read our cached copy of IR page (investors.terawulf.com) (https://d1io3yog0oux5.cloudfront.net/_0c87b48cb4d1c6967968c7d0c3e5933d/terawulf/db/2396/23300/pdf/WULF_Nautilus_Sale_Announcement_Deck_%2810-03-24%29vF.pdf) in full (14,394 characters, retrieved September 1, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Nautilus Sale Announcement
Quote: “CB-1: 20 MW capacity expected to be operational in Q1 2025”
delays TeraWulf 10-Q filed 2025-05-09
Quote: “supporting up to 72.5 MW of data center infrastructure dedicated to GPU compute workloads. This capacity is expected to come online throughout 2025.”
delays View 10-K PDF
Quote: “The Company commenced HPC leasing operations at the Lake Mariner Data Campus in July 2025”