72.5 MW HPC hosting capacity at Lake Mariner
Company: TeraWulf
What the later record shows
The date slipped · new target December 31, 2025
In August 2025, after the Q2 deadline, the 10-Q still described the 72.5 MW as 'expected to come online throughout 2025', and CB-2 (50 MW) was moved to Q4 delivery. WULF Den and CB-1 came online in July–August 2025, so part of the capacity was delivered late.
“supporting up to 72.5 MW of data center infrastructure dedicated to GPU compute workloads. This capacity is expected to come online throughout 2025.”
2025-08-07 · TeraWulf 10-Q filed 2025-08-08 View cached copy (2026-08-31)Live source ↗
“x WULF Den began recording revenue in July x CB - 1 will begin recording revenue mid - August x CB - 2 on track for Q4 delivery”
2025-08-13 · terawulf 8-K exhibit (tm2523008d1_ex99-3.htm) View cached copy (2026-10-06)Live source ↗
Checked October 25, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
TeraWulf is targeting delivery of 72.5 MW of HPC hosting capacity at Lake Mariner by the end of Q2 2025, an accelerated timeline funded by the Nautilus sale proceeds and the convertible notes financing.
Source (primary)
terawulf 8-K exhibit (wulfopsreport-202410oct2.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-25)Live source ↗
Quote: “We are targeting the delivery of 72.5 MW of HPC hosting capacity by the end of Q2 2025”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms terawulf 8-K exhibit (wulfopsreport-202410oct2.htm)
Quote: “We are targeting the delivery of 72.5 MW of HPC hosting capacity by the end of Q2 2025”
delays TeraWulf 10-Q filed 2025-08-08
Quote: “supporting up to 72.5 MW of data center infrastructure dedicated to GPU compute workloads. This capacity is expected to come online throughout 2025.”
delays terawulf 8-K exhibit (tm2523008d1_ex99-3.htm)
Quote: “x WULF Den began recording revenue in July x CB - 1 will begin recording revenue mid - August x CB - 2 on track for Q4 delivery”