Lake Mariner Building 5 online
Company: TeraWulf
What the later record shows
Delivered late · happened April 30, 2025
The company said in November 2024 that the 50 MW building would be operational in Q1 2025. The May 2025 presentation states that the 50 MW MB-5 expansion came online in April 2025, which is after Q1 2025.
“currently constructing an additional 50 MW facility, which we expect to be operational in the first quarter of 2025”
2024-11-11 · TeraWulf 10-Q filed 2024-11-12 View cached copy (2026-08-31)Live source ↗
“225 MW in operation Q1 2025 ➢ 50 MW (MB-5) expansion online April 2025”
2025-05-08 · Investor Presentation View cached copy (2026-09-01)Live source ↗Archive.org ↗
Checked November 4, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
TeraWulf has optimized a 50 MW modular building design for Building 5, currently anticipated to be online in Q1 2025.
Source (primary)
terawulf 8-K exhibit (wulfmay24opsreportdraft0.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-04)Live source ↗
Quote: “we have already optimized a 50 MW modular building with local key contractors for Building 5, which is currently anticipated to be online in Q1 2025”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms terawulf 8-K exhibit (wulfmay24opsreportdraft0.htm)
Quote: “we have already optimized a 50 MW modular building with local key contractors for Building 5, which is currently anticipated to be online in Q1 2025”
confirms TeraWulf 10-Q filed 2024-11-12
Quote: “currently constructing an additional 50 MW facility, which we expect to be operational in the first quarter of 2025”
confirms Investor Presentation
Quote: “225 MW in operation Q1 2025 ➢ 50 MW (MB-5) expansion online April 2025”