Lake Mariner facility miner deployment

Company: TeraWulf - Project: Lake Mariner Anthropic AI Factory

This claim was marked delayed on September 14, 2026. Recorded automatically from the cited source when it was published, then queued for evidence review.

How this was decided: Automated extraction from the cited source. The claim is preserved below exactly as it was originally published, so the record shows what was asserted as well as what became of it.

Subject kind
facility timeline
Statement date
2024-01-01
Promised by
2024-02-01
Promised amount
18500.0 units
Current status
delayed

The claim, verbatim

Company expects all 18,500 miners to be deployed at Lake Mariner facility on or about February 1, 2024

Source (primary)

TeraWulf 8-K filed 2024-01-02 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗

Quote: “the Company expects all 18,500 Miners to be deployed at its Lake Mariner facility on or about February 1, 2024.”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms TeraWulf 8-K filed 2024-01-02

Quote: “the Company expects all 18,500 Miners to be deployed at its Lake Mariner facility on or about February 1, 2024.”

View cached copy (2026-09-13)Live source ↗

Record of changes

September 13, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 14, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.