CB-3 delivery at Lake Mariner
Company: TeraWulf
What the later record shows
Delivered late · happened July 31, 2026
Energized HPC capacity was 81 MW at June 30, 2026, which is only 21 MW above the 60 MW delivered before CB-3. It reached 102 MW as of July 2026, when CB-3 (42 MW) was listed as delivered and operational, so full delivery came after the May target.
“As of June 30, 2026, TeraWulf had energized 81 critical IT MW of HPC leasing capacity at the Lake Mariner Data Campus.”
2026-08-04 · TeraWulf 10-Q filed 2026-08-05 View cached copy (2026-08-31)Live source ↗
“102 MW Energized and Generating Lease Revenue as of July 2026”
2026-08-04 · Q2 2026 Earnings Update Presentation View cached copy (2026-11-05)Live source ↗Archive.org ↗
“DELIVERED 102 MW ➢ WULF Den (2 MW) ➢ CB - 1 (16 MW) ➢ CB - 2A (21 MW) ➢ CB - 2B (21 MW) ➢ CB - 3 (42 MW)”
2026-08-04 · Q2 2026 Earnings Update Presentation View cached copy (2026-11-05)Live source ↗Archive.org ↗
Checked November 6, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
CB-3, a 42 MW critical IT building under construction, is scheduled for delivery in May 2026.
Source (primary)
Q1 2026 Earnings Update Presentation (IR page (investors.terawulf.com), ir_presentation)
View cached copy (2026-11-06)Live source ↗Archive.org ↗
Quote: “CB-3 (42 MW, May)”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms Q1 2026 Earnings Update Presentation
Quote: “CB-3 (42 MW, May)”
confirms TeraWulf 10-Q filed 2026-08-05
Quote: “As of June 30, 2026, TeraWulf had energized 81 critical IT MW of HPC leasing capacity at the Lake Mariner Data Campus.”
confirms Q2 2026 Earnings Update Presentation
Quote: “102 MW Energized and Generating Lease Revenue as of July 2026”