jain.com

CB-5 delivery Q4 2026

Company: TeraWulf - Project: Lake Mariner Anthropic AI Factory

Subject kind
facility timeline
Statement date
2026-02-26
Promised by
2026-12-31
Promised amount
168.0 MW
Current status
stated

The claim, verbatim

CB-5 building (168 MW critical IT) expected delivery in Q4 2026

Source (primary)

Q4 Earnings Update Presentation (IR page (investors.terawulf.com), ir_presentation)
View cached copy (2026-09-01)Live source ↗

Quote: “CB-5 (168 MW, Q4)”

How we checked this

Checked on October 14, 2026. The cited source supports every part of this claim.

The delivery-model slide lists 'CB-5 (168 MW, Q4)' under 2026 construction, in critical IT MWs. The construction slide confirms Q4 as the current estimate and says CB-5 capacity rose to 168 MW per building.

Confirmed in the source:

What we did: Read our cached copy of IR page (investors.terawulf.com) (https://d1io3yog0oux5.cloudfront.net/_0c87b48cb4d1c6967968c7d0c3e5933d/terawulf/db/2396/23307/pdf/TeraWulf_Q4_2025_Investor_Presentation_%28Feb_2026%29.pdf) in full (28,069 characters, retrieved September 1, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Q4 Earnings Update Presentation

Quote: “CB-5 (168 MW, Q4)”

View cached copy (2026-09-01)Live source ↗

confirms Q4 Earnings Update Presentation

Quote: “CB-5 (168 MW, Q4)”

View cached copy (2026-10-06)Live source ↗Archive.org ↗

confirms Q4 Earnings Update Presentation

Quote: “CB-5 (168 MW, Q4)”

View cached copy (2026-10-13)Live source ↗Archive.org ↗

Record of changes

September 2, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — stated
Review. statement_date 2026-09-01 was the source's retrieval date; source published 2026-02-26.