CB-5 data center delivery (168 MW critical IT)

Company: TeraWulf - Project: Lake Mariner Anthropic AI Factory

Subject kind
facility timeline
Statement date
2026-05-07
Promised by
2026-12-31
Promised amount
168.0 MW
Current status
stated

The claim, verbatim

CB-5 building (168 MW critical IT capacity) is progressing to delivery in Q4 2026

Source (primary)

terawulf 8-K exhibit (terawulfq12026investorpr.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-09-08)Live source ↗

Quote: “CB-4 / CB-5 progressing to delivery in 2026”

How we checked this

Checked on September 19, 2026. The cited source supports every part of this claim.

Slide 8 lists 'CB-5 (168 MW, Q4)' as critical IT MWs and slide 7 states CB-4/CB-5 are progressing to delivery in 2026.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1083301/000108330126000083/terawulfq12026investorpr.htm) in full (27,664 characters, retrieved September 8, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms terawulf 8-K exhibit (terawulfq12026investorpr.htm)

Quote: “CB-4 / CB-5 progressing to delivery in 2026”

View cached copy (2026-09-08)Live source ↗