CB-3 delivery (42 MW)

Company: TeraWulf - Project: Lake Mariner Anthropic AI Factory

Subject kind
facility timeline
Statement date
2026-05-14
Promised by
2026-05-31
Promised amount
42.0 MW
Current status
outcome unconfirmed

What the later record shows

Outcome not yet confirmed

No passage published after May 14, 2026 reports on CB-3's completion status.

Checked October 13, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

CB-3 (42 MW) is under construction and on track for completion in May 2026.

Source (primary)

Q1 2026 Earnings Update Presentation (IR page (investors.terawulf.com), ir_presentation)
View cached copy (2026-10-13)Live source ↗Archive.org ↗

Quote: “CB-3 (42 MW, May)”

How we checked this

Checked on October 15, 2026. The cited source supports every part of this claim.

The serial delivery slide lists CB-3 (42 MW, May) as under construction, and the 2026 execution slide says CB-3 is on track for completion.

Confirmed in the source:

What we did: Read our cached copy of IR page (investors.terawulf.com) (https://d1io3yog0oux5.cloudfront.net/_513c80c486e62e4bdb70115ded3782f5/terawulf/db/2396/23490/pdf/TeraWulf+Q1+2026+Investor+Presentation+%28May+2026%29.pdf) in full (27,753 characters, retrieved October 13, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Q1 2026 Earnings Update Presentation

Quote: “CB-3 (42 MW, May)”

View cached copy (2026-10-13)Live source ↗Archive.org ↗

Record of changes

October 13, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 13, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.