CB-3 delivery (42 MW)
Company: TeraWulf - Project: Lake Mariner Anthropic AI Factory
What the later record shows
Outcome not yet confirmed
No passage published after May 14, 2026 reports on CB-3's completion status.
Checked October 13, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
CB-3 (42 MW) is under construction and on track for completion in May 2026.
Source (primary)
Q1 2026 Earnings Update Presentation (IR page (investors.terawulf.com), ir_presentation)
View cached copy (2026-10-13)Live source ↗Archive.org ↗
Quote: “CB-3 (42 MW, May)”
How we checked this
Checked on October 15, 2026. The cited source supports every part of this claim.
The serial delivery slide lists CB-3 (42 MW, May) as under construction, and the 2026 execution slide says CB-3 is on track for completion.
Confirmed in the source:
- CB-3 is under construction as of March 31, 2026
- CB-3 is 42 MW of critical IT capacity
- CB-3 is on track for completion, targeted for May 2026
What we did: Read our cached copy of IR page (investors.terawulf.com) (https://d1io3yog0oux5.cloudfront.net/_513c80c486e62e4bdb70115ded3782f5/terawulf/db/2396/23490/pdf/TeraWulf+Q1+2026+Investor+Presentation+%28May+2026%29.pdf) in full (27,753 characters, retrieved October 13, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Q1 2026 Earnings Update Presentation
Quote: “CB-3 (42 MW, May)”